Santa Ana

City Council

March 21, 2023 Item #14

Agenda Item 14

14.\nApprove an Amendment to the Project Cost Analysis to add $343,000 to an Existing\nConstruction Contract with Big Ben, Inc. for a Revised Estimated Project Delivery Cost\nof $2,343,000, for the Lincoln Avenue Water and Sewer Main Improvements Project\n(Project Nos. 22-6468 and 22-6620) (Non-General Fund)\nDepartment(s): Public Works Agency\nRecommended Action: Approve an amendment to the Project Cost Analysis to reflect\nthe new amount of $571,235 for project contingency for unanticipated or unforeseen\nwork, for a total construction delivery cost of $2,343,000, subject to non-substantive\nchanges approved by the City Manager and City Attorney.