16. 25-358 Accept the lowest responsive and responsible bid and authorize\nexecution of a construction contract with Power Engineering\nConstruction Company in the amount of $353,068 for the Bolsa\nAvenue Bridge Maintenance Project, CC-1745; approve\nsupplemental construction costs; and authorize 15% in contingency\nfunds\nRecommended Action:\nA) Accept the lowest and responsible bid submitted by Power Engineering Construction\nCompany in the amount of $353,068;\nB) Authorize the Director of Public Works to approve change orders up to 15%\ncontingency in potential construction change orders; and ,\nC) Authorize the Mayor and City Clerk to execute a construction contract with Power\nEngineering Construction Company in a form approved by the City Attorney.