Glendale
City Council
Agenda Item a
a. Glendale Water and Power, re: Request to Increase the ARB, Inc. Balance of Site\nEngineering, Procurement, and Construction Contract’s current Contingency of\n$36,270,000 by $30,000,000 to a New Contingency Amount of $66,270,000 as it\nRelates to the Potential Tariffs which may be Imposed on Various Equipment for the\nGrayson Repowering Project\n1. Motion increasing the ARB, Inc. Balance of Site Engineering, Procurement, and\nConstruction Contract’s, Contract No. 8002399, current Contingency of $36,270,000\nby $30,000,000 to a New Contingency Amount of $66,270,000\n2. Resolution of Appropriation requesting $30,000,000 for Contract No. 8002399 with\nARB, Inc