Covina
City Council
Agenda Item 5
CC 5. Amending the Fiscal Year 2024/2025 Capital Improvement Program to Increase\nFunding for the Covina Recreation Village Project and Authorize the Director of Public\nWorks to Approve a Change Order for the Construction of Phase II - Library\nStaff Recommendation:\n1. Approve plans and specifications for the Covina Recreation Village Project Phase II\n– Library;\n2.\nAdopt Resolution CC 2025-40 appropriating $4,179,776.36 from various funding\nsources to the Covina Recreation Village Project in order to provide additional\nfunding for the construction of Phase II – Library;\n3.\nAuthorize the Director of Public Works/City Engineer to approve a contract change\norder for the Covina Recreation Village Project to Perera Construction and Design,\nInc. in the amount of $9,276,796.36 for the construction of the new library building;\nand\n4.\nAuthorize a project contingency amount of $565,281.10 to cover the cost of\nunforeseen construction expenses.