Chino

City Council

April 04, 2023 Item #18

Agenda Item 18

18. Notice of Completion - MS202/ST221 Sidewalk/Crossing Access Improvements and Norton Cul-\nde-Sac. Accept Project No. MS202/ST221 - Sidewalk/Crossing Access Improvements and\nNorton Cul-de-Sac as complete and authorize the Director of Public Works to file the Notice of\nCompletion.\nStaff Report by: Maria Fraser, CIP Engineering Manager.\nRECOMMENDATION: 1) Accept Chino Avenue and Norton Avenue Cul-De-Sac Accessibility\nImprovement Project (MS202 and ST221) by EBS General Engineering, Inc., Corona, CA,\nContract 2022-311, as complete; 2) release the retention funds following the 35-day lien period;\nand 3) authorize the Director of Public Works to file the Notice of Completion.\nM _____ S _____ RC _____