10.10\nContract Change Order with Optima RPM, Inc. for the Central Park Amphitheater\nProject\nRECOMMENDED ACTION\n1. Approve and authorize the City Manager to execute Contract Change Order No.\n7 with Optima RPM, Inc. for the Central Park Amphitheater Capital Improvement\nProgram (CIP) Project No. 19-15, increasing the contract amount by\n$182,499.11, for a total contract value amount not-to-exceed $5,574,298.22, and\nincreasing the working days by 67, for a total amount of 398 working days; and\n2. Adopt two budget amendment resolutions appropriating $47,396 for the transfer\nout of the Development Impact Fee (DIF) Citywide – Park Improvements Fund\n2522 and the transfer in and expenditures within the Capital Projects Fund 4320\nto the Project account.