Whittier

City Council

October 28, 2025 Order of Business 8 #E

Agenda Item E

8.E.\n25-024 Bailey Street Sewer Replacement Project – Award of Contract\nRecommendation:\n1)\nAward the construction contract to Ramona, Inc., in the amount of\n$674,750;\n2) Reject all other bids;\n3) Authorize the Executive Director to execute the construction contract on\nbehalf of Whittier Utility Authority; and\n4) Approve $67,475 in contingency funding subject to the approval of the\nExecutive Director.