Fullerton
City Council
Agenda Item 6
6.\n$899,9 8 5 P R O F E S S I O N A L\nENGINEERING, INC. FOR\nIMPROVEMENT PROJECT SERVICES THE HARBOR AGREEMENT\nWITH BOULEVARD COMPLETE DOKKEN STREETS\nProposed Motion:\n1. Approve $90,000 Measure M2 Funds (Fund 25) budget transfer and appropriation\nfrom fund balance to Project 48009 Harbor Boulevard Complete Streets Improvement\nProject within the Capital Projects Fund (Fund 74).\n2. Approve and authorize City Manager, or designee, to execute a $899,985\nProfessional Services Agreement with Dokken Engineering, Inc., for the Harbor\nBoulevard Complete Streets Improvement Project design services.\n3. Authorize Administrative Services Director, or designee, to issue $899,985 purchase\norder to Dokken Engineering, Inc., for the Harbor Boulevard Complete Streets\nImprovement Project.\nNovember 4, 2025 - Page 4\n4. Authorize Public Works Director, or designee, to approve\nprofessional engineering services within the approved project budget.\nchange orders\nfor