Chino Hills
City Council
Agenda Item 11
11.\nAppropriate $500,000 from Water Utilities Fund; award contract to SCW Contracting\nCorporation in amount of $568,662 for construction of Well 5 Metering Station (1,2,3-TCP\nTreatment Plant Blending Plan Compliance Facility) Project (Project); authorize City\nManager, at his discretion, to approve cumulative change orders up to ten percent\n($56,866.20) of awarded contract amount; authorize execution of Change Order No. 2 to\nAgreement No. A2024-095 with George T. Hall Company, Inc., increasing contract amount to\n$760,905.56 for additional scope of work including installation of SCADA/Telementry\nequipment, programming, and integration of SCADA system for Project and other related\nwork; and authorize City Manager, at his discretion, to approve cumulative change orders up\nto ten percent ($67,597.04) of original awarded amount to Agreement No. A2024-095 for\nanticipated change orders during construction of Project through final phases of 1,2,3-TCP\nTreatment Plant fully operational start-up