B.6. NOTICE\nOF\nCOMPLETION\nFOR\n8305\nSANTA\nMONICA\nBOULEVARD BUILD-OUT PROJECT [H. COLLINS, P. TICUN, K.\nTRUDEAU, D. GONZALEZ]:\nSUBJECT: The City Council will consider approving the Notice\nof Completion for the 8305 Santa Monica Boulevard Build-Out\nProject performed by PCL Construction Services, Inc.\nRECOMMENDATION: Accept the work and authorize the\nfollowing: a) File the Notice of Completion with the City Clerk\nfor recording with the Los Angeles County Registrar-\nRecorder/County Clerk, b) Issue the final payment to the\ncontractor at the end of the 35-day lien period, c) Release of the\nPerformance Bond on the date of recordation of the Notice of\nCompletion, and d) Release of the Payment Bond 35 days after\nthe date of recordation of the Notice of Completion, pending no\nreceipt\nof\nStop\nNotices\nfrom\nmaterial\nsuppliers\nor\nsubcontractors.\nSTAFF REPORT