Glendora
City Council
Agenda Item 11
11. Notice of Completion for CDGB-Funded Curb Ramp Project FY 2025-2026, Plan No. 1402
Recommended Action for the City Council:
— 1. Accept the completion of CDBG Funded Curb Ramp Project FY 2025-2026, Plan No. 1402 by SAVI
Construction, Inc.;
— 2. Approve the final contract amount of $247,400;
— 3. Authorize the Mayor or his designee to sign and file the Notice of Completion with the County of Los
Angeles Registrar-Recorder;
— 4. Authorize the Public Works Director to release the project retention of $12,370 to SAVI Construction, Inc.
35 days after the recordation of the Notice of Completion;
— 5. Authorize the release of the Labor and Materials Bond in the amount of $227,600 six months after
recordation of Notice of Completion, if no claims have been received; and
— 6. Authorize the release of the Faithful Performance Bond one (1) year following recordation of the Notice of
Completion if the improvements remain free from defects in materials and workmanship.