25.\nApprove Change Order and Revised Project Cost Analysis for an Existing Construction\nContract with iBuild Spectrum, Inc., for a Total Project Delivery Cost of $1,740,000, for the\nCampesino Park, Memorial Park, and Madison Park Restrooms (Project Nos. 21-7533,\n21-7534, 21-7535) (Non-General Fund) (Revive Santa Ana Program)\nDepartment(s): Public Works Agency\nRecommended Action: Authorize the City Manager to approve Change Orders and\nrevise the Project Cost Analysis to reflect a transfer of savings from construction\nadministration and inspection to contingency in an amount of $33,898, with a total Project\nDelivery Cost of $1,740,000.