Agenda Item 13
13. Hot Spot Intersection Improvements at Rosemead Boulevard and Beverly\nBoulevard (CIP No. 21276), Lindell Avenue Block Wall (Project) — Award of\nConstruction Contract. (500)\nRecommendation:\n1. Award a construction contract for a not-to-exceed amount of $107,000 to\nHZS Engineering dba HZS Construction for the Project and authorize the\nCity Manager to execute the contract in a form approved by the City Attorney;\n2. Authorize the City Manager to approve change orders, as needed, in an\namount not-to-exceed $10,700, (approximately 10% of the total contract\namount) for construction contingency.\nAgreement No.