6.3. Award of Contract to Environmental Construction, Inc. for Well No. 28 Equipping\nProject, Bid No. 22-23.33; increase to the capital improvement project budget;\nand finding of CEQA exemption.\nRecommended Action:\n1. Authorize the appropriation of $1,270,000 to expenditure account number\n550.8011.56411.18120, Reimbursable Capital Projects - Well 28 Construction.\n2. Approve contract with Environmental Construction, Inc. in the total amount of\n$8,593,377.65, representing an original amount of $7,812,161.50 plus a 10%\ncontingency of $781,216.15, for Well 28 Equipping Project; and authorize the\nMayor and City Clerk to execute on behalf of the City.\nAttachments: Staff Report\nLocation Map\nBid Abstract\nContract with ECI\nPFAS Treatment Facilities and Program Agreement\nSARCCUP Agreement