3. Approval of Funds Appropriation to Cover Construction Change Orders for\nthe Foster Drainage Improvements Project - CIP 21-190\nIt is recommended that the City Council: Authorize the additional work and\npayment for VCWD in the amount of $33,711.30 for the relocation of\nexisting water main and shut off valve; and, Authorize the Director of\nPublic Works to negotiate and execute construction change orders for\nunforeseen conditions during construction in the amount of $208,274.28\n(Attachment 1); and, Authorize the Director of Finance to appropriate\n$50,000 from Fund 255 to Account No. 255-50-520-58100-15105 and\n$60,000 from Fund 258 to Account No. 258-50-520-58100-15105 and to\nmake the necessary budget adjustments.\nSTAFF REPORT