Brea
City Council
Agenda Item 16
16. Award Contract with Kana Pipeline, Inc. for the Associated Road High-Pressure Water\nLine, CIP No. 7476 (Project) - Approve the Plans and Specifications; Receive bids; Award\nContract to the lowest responsive and responsible bidder, Kana Pipeline, Inc.for\n$2,399,420.00; and, Authorize the City Engineer to issue Change Orders up to a "not-to-\nexceed" amount of 10% of the Contract Price. The approved FY 2023-24 CIP Project budget\nfor Construction and Construction Engineering is $2,750,000. The total cost for Construction\nand Construction Engineering is $2,748,362, which includes the apparent low bid amount of\n($2,399,420), a 10% contingency ($239,942), and Construction Engineering costs ($109,000).\nThe funds within the approved budget are from the Water Fund (Fund 420) and Gas Tax (Fund\n220).