5) CONSIDERATION OF ACCEPTANCE OF WORK ON AZUSA AVENUE SEWER LIFT\nSTATION UPGRADES PROJECT – PROJECT NO. U-17022\nIt is recommended that the City Council take the following actions:\n1. Accept the work performed by Pyramid Building & Engineering, Inc. for the Azusa\nAvenue Sewer Lift Station Upgrades Project (Project No. U-17022), with a final contract\namount of $3,692,129.16; and\n2. Authorize the release of retention funds once appropriate.\nFINANCE DEPARTMENT