Agenda Item
· Placentia
City Council — Item F
Original agenda text
Order of Business 1
1.f. Acceptance of Construction Work and Notice of Completion
for the ADA Access Ramp Installation Project, City Project
No. 1305 Fiscal Impact: Expense: $175,050.00
Construction Contract $-40,940.00 Change Order No. 1
$134,110.00 Total Construction Cost Available Budget:
$192,600.00 Total FY 2022-23 CIP Budget $192,600.00
Measure U Fund (791305-6740)
1) Authorize the City Administrator to approve Contract
Change Order No. 1 with Martinez Concrete, Inc., in
the credit amount of $40,940.00; and
2) Accept the work performed by Martinez Concrete,
Inc., for construction of the ADA Access Ramp
Installation Project, City Project No. 1305 for a grand
total amount of $134,110.00; and
3) Authorize the City Administrator to file a Notice of
Completion with the Orange County Clerk-Recorder’s
Office for the Project; and
4) Authorize the City Administrator to release retention
funds in accordance with the terms of the contract.
Staff Report
Contract Change Order #1
NOC
Before and After Photos