13. Change Order No. 1 to Contract No. 2022-84-CC with NR Development, Inc., for the
Hollydale Community Park, City Project No. 607-PRK
The City Council will consider: (PW)
a. Approving Contract Change Order No. 1 to Contract No. 2022-84-CC with NR
Development, Inc., to supplant the construction of decomposed granite with rubber
surfacing for the perimeter pathway on the Hollydale Community Park, City Project No. 607-
PRK, in a net amount of $55,365.12;
b. Authorizing the Assistant City Manager/Public Works Director to execute Change Order No.
1;
c. Authorizing the City Manager to approve contract change orders up to a cumulative amount
of $400,000 to avoid delaying construction and payment of invoices involving change order
work; and
d. Authorizing the City Manager to approve pre-payments of construction progress payments
for the construction contract to meet compliance with state legislation that requires
payments within 30 days.