Agenda Item
· Santa Clarita
City Council — Item 10
Original agenda text
Item
10. 2022-23 ANNUAL CONCRETE REHABILITATION PROGRAM, PROJECT
M0148 AND 2022-23 ADA ACCESS RAMPS, PROJECT D0003 - PLANS AND
SPECIFICATIONS AND CONSTRUCTION CONTRACT - The sidewalk repair
program will replace selected existing sidewalks damaged by tree roots and pavement
settlement. The access ramp construction program will serve people with disabilities
through the installation of new access ramps.
RECOMMENDED ACTION:
City Council:
1. Approve the plans and specifications for the 2022-23 Concrete Rehabilitation
Program, Project M0148, and 2022-23 ADA Access Ramps, Project D0003.
2. Award the construction contract to Toro Enterprises, Inc., in the amount of $643,160
and authorize a contingency of $10,000 for the total contract amount of $653,160.
3. Authorize the transfer of project savings in the amount of $100,000 to 2022-23
Concrete Rehabilitation Program expenditure account M0148233-516101 from the
following accounts:
• $38,000 in TDA Article 8 Street & Road (Fund 233) from expenditure account
T3027233-516101, Sidewalk Gap Closure;
• $37,000 in TDA Article 8 Street & Road (Fund 233) from expenditure account
M0147233-516101, 21-22 Thermoplastic Lane Striping; and
• $25,000 in TDA Article 8 Street & Road (Fund 233) from expenditure account
C0064233-516101, 20-21 Circulation Improvement Program.
4. Authorize the City Manager or designee to execute all documents, subject to City
Attorney approval.