RESOLUTION NO. - Change Order 3 to Contract DA-5570 with Hensel Phelps
Construction Company: For $2,252,749, to provide design and construction services for the
Terminal 2 Federal Inspection Services Facility at Los Angeles International Airport, to add an
additional amount of $3,066,200 in project contingency, and to appropriate funds in amount of
$5,318,949
PURPOSE: Delta Air Lines is currently embarking on a Modernization Program of Terminal 2
(T2) and Terminal 3 (T3) which replaces T3 and renovates portions of T2. In conjunction with
said program, Los Angeles World Airports is refurbishing the T2 Federal Inspection Services
facility to meet certain standards of the United States Customs Service-Customs and Border
Patrol (CBP) component of the Department of Homeland Security, The project will improve
guest experience for incoming international travelers arriving in T2 and T3. The Board of
Airport Commissioners action is to increase the contract value of the design-builder to cover
certain CBP requirements, address unforeseen conditions, owner betterments, regulatory scope
and provide additional contingency to address potential future unforeseen conditions for the
remainder of the project.
13.
RECOMMENDATIONS: Adoption of the Report requesting that the Board of Airport
Commissioners determine that this action is exempt from the California Environmental Quality
Act (CEQA) pursuant to Article II, Section 2.i and Article III, Class 1 (1) of the Los Angeles
City CEQA Guidelines; approve Change Order 3 to Contract DA-5570 with Hensel Phelps
Construction Company; further approve an increase in the budgeted Owner's Contingency in
amount of $3,066,200, bringing the total to $3,366,200, that can only be utilized through
change orders authorized by the Chief Executive Officer, or designee, or the Board of Airport
Commissioners; further approve appropriation of $5,318,949 to the Terminal 2 Federal
Inspection Services Facility Refurbishment Project that includes $2,252,749 in hard costs and
$3,066,200 in additional Owner's Contingency; authorize the Chief Executive Officer, or
designee, to approve and execute change orders to the contract up to the budgeted Owner's
Contingency of $3,366,200 for the project provided that, prior to execution of any change order
in excess of $500,000, the Board of Airport Commissioners shall first have reviewed and
authorized execution thereof, and such authorization shall have become final pursuant to City
Charter Section 245; and further authorize the Chief Executive Officer, or designee, to execute
said Change Order 3 to Contract DA-5570 after approval as to form by the City Attorney. (Hans