2.L. INCREASE IN PROJECT CONTINGENCY FOR THE CITY’S
CONTRACT WITH KORDICH CONSTRUCTION AND APPROVE
THE NOTICE OF COMPLETION FOR THE WESTBOURNE DR
WATER SEEPAGE MITIGATION CIP 2105 [S. CAMPBELL, J.
GILMOUR]:
The City Council will consider increasing the project contingency for
the Westbourne Drive Water Seepage Mitigation CIP 2105 by
$20,361.75 to account for changes in the construction agreement
with Kordich Construction due to unforeseen conditions, for a total
not to exceed amount of $114,087.15, and approving the Notice of
Completion for the project.
RECOMMENDATIONS: 1) Authorize a $20,361.75 increase in the
contingency amount for Construction Services with Kordich
Construction, for a new not to exceed contingency amount of
$114,087.15 and authorize the City Engineer to approve change
orders to the agreement for services; 2) Authorize the City Manager
or designee to execute all documents incident to the Agreements;
3) Accept the work and authorize the following: a. File the Notice of
Completion by the City Clerk with the Los Angeles Recorder's
Office, b. Issue the final payment to the contractor at the end of the
35 day lien period, c. Release of the Performance Bond on the date
of recordation of the Notice of Completion, d. Release of the
Payment Bond 35 days after the date of recordation of the Notice of
Completion, pending no receipt of Stop Notices from material
suppliers or subcontractors.