Santa Ana
City Council
11.
Approve an Amendment to the FY 2022-23 Capital Improvement Program for $752,471.25
and Award a Construction Contract to International Line Builders, Inc. in the Amount of
$601,977.00 for the Saddleback View Neighborhood Street Lighting Project, with an
Estimated Project Delivery Cost of $752,471.25 (Project No. 22-6017) (General Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an amendment to the FY 2022-23 Capital
Improvement Program to include $752,471.25 in construction funds for the Saddleback
View Neighborhood Street Lighting Project (Project No. 22-6017).
2. Award a construction contract to International Line Builders, Inc., the lowest responsible
bidder, in accordance with the base bid in the amount of $601,977.00, for construction of
the Saddleback View Neighborhood Street Lighting Project, for the term beginning March
7, 2023, and ending upon project completion, and authorize the City Manager to execute
the contract subject to non-substantive changes approved by the City Manager and the
City Attorney.
3. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$752,471.25, which includes $601,977.00 for the construction contract, $90,296.55 for
contract administration, inspection and testing, and a $60,197.70 project contingency for
unanticipated or unforeseen work.