12. NOTICE OF COMPLETION: PURCHASE OF SHADE STRUCTURES FOR ALHAMBRA
AND GRANADA PARK POOLS – F2M22-6B, C2M22-10, M2M23-34
On March 14, 2022, the City Council awarded a contract to Pacific Play Systems Inc. for
the Alhambra Pools Shade Structure Project in the amount of $249,500.00. There were
two change orders totaling $24,009.25 for the project for additional drilling due to finding
water lines and to move one shade from Granada Pool to Alhambra Pool due to finding
unforeseen concrete in the excavation process. The total amount of the contract is
$273.509.25. This project has been inspected by staff, and all work has been completed
in accordance with the City’s requirements and specifications. As such, it would be
appropriate for the City Council to accept this project as complete.
Recommended Action: City Council accept the work of Pacific Play Systems Inc. for
the Alhambra Pools Shade Structure Project as complete in the amount of $273,509.25;
direct the City Clerk to file a Notice of Completion with the County of Los Angeles for
recordation; instruct the Finance Director to release the 5 percent retention 35 days from
the date of recordation if no liens are filed; and, direct staff to undertake the steps
necessary to finalize Council’s action. (M2M23-34)