Santa Ana
City Council
15.
Approve Appropriation Adjustments and Award a Construction Contract to GMZ
Engineering, Inc. in the amount of $4,642,644 for the Downtown Flood Reduction and
Stormwater Infiltration Project with an Estimated Construction Delivery Cost of
$5,640,000 (Non-General Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an appropriation adjustment to recognize an
additional $1.25 million in Proposition 68 Urban Flood Protection (UFP) grant funding
from the California Natural Resources Agency into the Public Works Agency Enterprise
Capital Grants, Direct Revenue Account and appropriate the same amount into the
California Natural Resources Agency Urban Flood Protection, Improvements Other Than
Building expenditure account. (Requires five affirmative votes)
2. Approve an appropriation adjustment to recognize $900,000 of prior year fund
balance in the Federal Clean Water Protection fund, Prior Year Carryforward revenue
account and appropriate the same amount into the Federal Clean Water Protection
Enterprise, Improvements Other Than Building expenditure account. (Requires five
affirmative votes)
3. Approve an amendment to the Fiscal Year 2022-23 Capital Improvement Program to
add $1.25 million of Proposition 68 Urban Flood Protection Grant Program funding and
$900,000 of Federal Clean Water Protection Enterprise funding for the Downtown Flood
Reduction and Stormwater Infiltration Project (22-6622).
4. Award a construction contract to GMZ Engineering Inc., the lowest responsible bidder,
in accordance with the base bid plus bid alternate in the amount of $4,642,644, for
construction of the Downtown Flood Reduction and Stormwater Infiltration Project, for
the term beginning March 21, 2023 and ending upon project completion, and authorize
the City Manager to execute the contract subject to non-substantive changes approved
by the City Manager and the City Attorney.
5. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$5,640,000, which includes $4,642,644 for the construction contract, $552,356 for
contract administration, inspection and testing, and a $445,000 project contingency for
unanticipated or unforeseen work.
(includes determination that the recommended actions are exempt from further review in
accordance with the California Environmental Quality Act (CEQA) as Categorical
Exemption Environmental Review No. ER-2022-95 was filed for the project)