Agenda Item
· Signal Hill
City Council — Item A
Original agenda text
Order of Business 12
a. MEMORANDUM OF UNDERSTANDING (MOU) WITH CITY OF LONG BEACH
AND PUBLIC WORKS CONTRACT WITH INTERNATIONAL LINE BUILDERS,
INC. DBA ILB ELECTRIC FOR EAST 20TH STREET AND REDONDO
AVENUE INTERSECTION IMPROVEMENT PROJECT (PROJECT NO.
90.20007)
Summary:
Staff recommends the City Council consider entering into an MOU with City of
Long Beach and a Public Works Contract with ILB Electric for construction of the
East 20th Street and Redondo Avenue Intersection Improvement Project. This
scope of work for this Project includes the following tasks:
· Installation of new traffic signal poles and foundations, signal mast arms,
LED luminaire, signal heads, countdown pedestrian heads, pedestrian
push buttons, pedestrian push button signs, pullboxes, PVC conduits (3”),
and conductors;
· Installation of Type E and Type D inductive vehicle detector loops;
· Traffic striping and installation of internally illuminated street name sign;
and
· Installation of grated line drain, and curb ramp per Caltrans Standard
Plans D98H and A88A, Case C respectively.
Recommendations:
1. Authorize the City Manager to enter into an MOU with City of Long Beach for
construction of the project, in a form approved by the City Attorney.
2. Authorize the City Manager to enter into a Public Works Contract with ILB
Electric for construction of the Project, in a form approved by the City
Attorney. The term of the agreement is for 90 working days upon issuance of
Notice to Proceed with a not-to-exceed contract amount of $448,479.00.
3. Authorize contingencies of 10% ($44,847.90) and up to a 180-day term
extension pursuant to the City’s Purchasing and Contracting Guidelines, to
be utilized if approved by the Public Works Director.