Agenda Item
· Signal Hill
City Council — Item B
Original agenda text
Order of Business 12
b. PUBLIC WORKS CONTRACT WITH PALP, INC. DBA EXCEL PAVING
COMPANY (EXCEL PAVING) FOR OHIO AVENUE STREET REHABILITATION
FROM HILL STREET TO SKYLINE AVENUE (PROJECT NO. 90.23003)
Summary:
The City Council will consider entering into a Public Works Contract with Excel
Paving for construction of the Ohio Avenue Street Rehabilitation Project from Hill
Street to Skyline Avenue (Project No. 90.23003). The Project includes:
· Approximately 26,000 square feet of asphalt pavement repair employing
a combination of reconstruction and grind/overlay;
· Removal and replacement of approximately 560 square feet of damaged
sidewalk;
· Restoration of traffic striping and markings; and
· Upgrade of two ADA access ramps.
Recommendations:
1. Authorize the City Manager to enter into a Public Works Contract with Excel
Paving for construction of the Ohio Avenue Street Rehabilitation Project from
Hill Street to Skyline Avenue (Project No. 90.23003), for a term of 40
calendar days and a not-to-exceed contract amount of $294,491.40 in a form
approved by the City Attorney.
2. Authorize a contingency of 10% ($29,449) to accommodate additional scope
of work and changed or unforeseen conditions to be utilized if approved by
the Public Works Director for a total construction budget of $323,940.40.