Agenda Item
· Fullerton
City Council — Item 16
Original agenda text
Item
16. ELLIS PLACE SEWER REPLACEMENT AND STREET IMPROVEMENTS
PROJECT
April 18, 2023 - Page 7
Recommendation:
1. Approve plans and specifications for Ellis Place Sewer Replacement and Street
Improvements Project.
2. Approve the following budget appropriations to Project 51020 Ellis Place Sewer
Replacement and Street Improvements Project:
· $316,000 budget transfer and appropriation of Sewer Enterprise Funds from
Project 51419 Annual Sewer Replacement Project (Fund 47).
· $335,000 budget transfer and appropriation of Measure M2 Funds (Fund 74) from
Project 44589 Annual Residential Street Program.
3. Award $493,190 construction contract for Ellis Place Sewer Replacement and Street
Improvements Project to Palp, Inc. DBA Excel Paving Company and authorize City
Manager, or designee, to execute the contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve any future change orders for
construction and professional engineering construction support services within the
approved project budget.