Santa Ana
City Council
13.
Award a Construction Contract to Diamond Construction & Design in the Amount of
$1,374,150 for the Kennedy Elementary and Villa Fundamental Intermediate Safe Route to
School (SRTS) Project With an Estimated Project Delivery Cost of $1,659,049 (Project No.
20-6963, ATPSB1L-5063(199) (General and Non-General Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an amendment to the Fiscal Year 2022-23 Capital
Improvement Program to include $130,000 of funding in General Fund for the Kennedy
Elementary and Villa Fundamental Intermediate SRTS.
2. Authorize the reallocation of unspent Measure M2 Local Fairshare funds from various
projects; $128,316 from Bike Lane Project Development, $84,733 from Traffic Safety
Project Development, and $25,000 from the Jackson Elementary Improvements Project,
for a total of $238,047 to the Kennedy Elementary and Villa Fundamental Intermediate
SRTS Project to complete the project’s funding requirement.
3. Award a construction contract to Diamond Construction & Design, the lowest
responsible bidder, in accordance with the base bid in the amount of $1,374,150, for
construction of the Kennedy Elementary and Villa Fundamental Intermediate SRTS
Project, for the term beginning April 18, 2023, and ending upon project completion, and
authorize the City Manager to execute the contract subject to non-substantive changes
approved by the City Manager and the City Attorney.
4. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$1,659,049, which includes $1,374,150 for the construction contract, $147,484 for contract
administration, inspection, and testing; and a $137,415 project contingency for
unanticipated or unforeseen work.
5. Determine that the recommended actions are exempt from further review in accordance
with the California Environmental Quality Act as Categorical Exemption Environmental
Review No. ER-2020-96 was filed for Project 20-6963.