10. AWARD CONTRACT: MAIN STREET SEWER MAIN REPLACEMENT PROJECT
BETWEEN GRANADA AVENUE AND EL MOLINO STREET – F2M23-26, N2M23-24,
C2M23-26, M2M23-57
On February 27, 2023, the City Council approved the distribution of a Notice Inviting Bids
for the Main Street Sewer Main Replacement Between Granada Avenue and El Molino
Street. On March 30, 2023, bids were opened by the City Clerk. Ten bids were received,
which ranged from base bid amounts of $673,020 to $1,622,700. GRBCON Inc. submitted
the lowest qualified bid at $673,020.00. In addition to base bid amount, GRBCON Inc.
submitted $37,859.00 under the Alternative Bid Schedule. Staff reviewed the bid
submitted by GRBCON Inc. and found it to be in full compliance and conformance with
the project specifications.
5
4-24-23
Recommended Action: City Council award a contract, subject to final language
approval by the City Manager and City Attorney, by and between the City of Alhambra and
GRBCON Inc., for the Main Street Sewer Replacement Project between Granada Avenue
and El Molino Street in an amount not to exceed $710,879.00; find the Main Street Sewer
Replacement Project between Granada Avenue and El Molino Street categorically exempt
from California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section
15301 (b); and, direct staff to undertake the steps necessary to finalize Council’s action.
(M2M23-58)