Agenda Item
· Irvine
City Council — Item 6
Original agenda text
Order of Business 3
3.6 APPROVAL OF PLANS, SPECIFICATIONS, AND CONTRACT
DOCUMENTS FOR CITYWIDE CATCH BASIN CONNECTOR
PIPE SCREEN INSTALLATION PROJECT PHASE 3
ACTION:
1) Approve the construction plans, specifications, and contract
documents for the Citywide Catch Basin Connector Pipe
Screen Installation Project Phase 3.
2) Authorize staff to award the contract in accordance with the
City's procurement and competitive bidding procedures, within
the approved project budget.
3) Approve a new capital improvement project in the amount of
$206,400 for Citywide Catch Basin Connector Pipe Screen
Installation Project Phase 3.
4) Approve a budget adjustment for $206,400 for the new
capital improvement project.
5) Approve the engineer's estimate, construction contingency
and funding summary.
3.6