Agenda Item
· Signal Hill
City Council — Item A
Original agenda text
Order of Business 8
a. RESOLUTION DECLARING FINAL ACCEPTANCE OF WELL NO. 8
DEMOLITION AND WELL NO. 10 CONSTRUCTION (PROJECT NO. 95.18011)
PURSUANT TO THE PUBLIC WORKS CONTRACT WITH PASCAL & LUDWIG
CONSTRUCTORS, INC. (P&L)
Summary:
Pascal & Ludwig (P&L) completed the work for the Well No. 8 Demolition and
Well No. 10 Construction (Project No. 95.18011) to the satisfaction of the Public
Works Department and in accordance with the project plans and specifications.
Final cost of the construction was $3,143,765.15. Well 10 will be operational
once the State Water Board issues a permit, anticipated after Summer 2023.
Staff is recommending final acceptance of the work performed by P&L and
issuance of final payment.
Recommendation:
Adopt a resolution, entitled:
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SIGNAL HILL,
CALIFORNIA, DECLARING WORK TO BE COMPLETED IN CONFORMANCE
WITH THE PLANS AND SPECIFICATIONS FOR THE WELL NO. 8
DEMOLITION AND WELL NO. 10 CONSTRUCTION (PROJECT NO. 95.18011)
IN THE CITY OF LONG BEACH, IN ACCORDANCE WITH THE CONTRACT
ENTERED INTO BETWEEN PASCAL & LUDWIG CONSTRUCTORS, INC.
AND THE CITY OF SIGNAL HILL