6. APPROVAL OF AMENDMENTS TO THE AGREEMENTS WITH CRANE
ARCHITECTURAL GROUP, KELLY SUTHERLIN MCLEOD
AGENDA – MAY 10, 2023 PAGE 3 of 6
ARCHITECTURE, AND GRIFFIN STRUCTURES; ADDITIONAL
HAZARDOUS MATERIAL ABATEMENT SERVICES BY VISTA
ENVIRONMENTAL; AND OF A PROFESSIONAL DESIGN SERVICES
AGREEMENT WITH CSI FULLMER FOR THE SAN MARINO
Council agrees with staff’s recommendation, an appropriate motion would be:“I move
to adopt Resolution No. R2315, Rescinding Resolution No.'s R2128 and R2218 to
Eliminate the Mandatory Vaccine Mandate for the Unrepresented Employees,
Employees Represented by the SMPOA and SMFFA, and Modifying the MOU with the
SMCEA.”
6. APPROVAL OF AMENDMENTS TO THE AGREEMENTS WITH CRANE
ARCHITECTURAL GROUP, KELLY SUTHERLIN MCLEOD
ARCHITECTURE, AND GRIFFIN STRUCTURES; ADDITIONAL
HAZARDOUS MATERIAL ABATEMENT SERVICES BY VISTA
ENVIRONMENTAL; AND OF A PROFESSIONAL DESIGN SERVICES
AGREEMENT WITH CSI FULLMER FOR THE SAN MARINO
COMMUNITY CENTER PROJECT
Recommendation: Staff recommends that the City Council approve the contract
amendments, additional hazardous material abatement services, and award a
professional design services agreement to CSI Fullmer. If the Council concurs, an
appropriate motion would be: “I move to approve Amendment No. 4 to the
professional design services agreement with Crane Architectural Group and increase
the compensation amount in the agreement, as modified by Amendments No. 1, 2,
and 3, by an additional $15,360; approve Amendment No. 1 to the professional
design services agreement with Kelly Sutherlin McLeod Architecture, Inc., increasing
the total compensation amount by $21,480; approve amendment No. 1 to the
professional services agreement with Griffin Structures increasing the total contract
amount by $65,000; authorize the procurement of additional hazardous materials
abatement services from Vista Environmental in the amount of $39,672; and award a
professional design services agreement in an amount not to exceed $275,000 to CSI
Fullmer for the design and procurement of furniture, fixtures, and equipment for the
San Marino Center.”