9. AWARD OF CONSTRUCTION CONTRACT FOR THE BLUEBIRD STORM
DRAIN OUTFALL AND DIVERSION STRUCTURE REHABILITATION
Recommendations:
(1) Award and authorize the City Manager to execute a contract with Beador
Construction Company, Inc., in the amount of $1,123,300, for the Bluebird Storm
Drain Outfall and Diversion Structure Rehabilitation;
(2) Authorize the City Manager to approve project related expenses and
construction change orders for unforeseen circumstances for an amount not-to-
exceed $150,000; and
(3) Transfer an appropriation of $404,000 in project savings from the Summit
Drive Storm Drain Improvement Project to the Bluebird Storm Drain Outfall
Project to fully fund the project.