14. AUTHORIZE RFP: DESIGN SERVICES FOR TRAFFIC SIGNAL SYNCHRONIZATION
PROJECT – ADAPTIVE/TRAFFIC RESPONSIVE UPGRADES PHASE 1 – F2M23-47,
RFP2M23-17
As part of a broader package of projects known as the SR-710 MIPs (Mobility
Improvement Projects), traffic signal synchronization projects were awarded by LACMTA
Measure R Funding. The SR-710 MIPs are the result of reallocated Measure R Funds for
the SR-710 North Project to new mobility improvement projects within the San Gabriel
Valley subregion. This project encompasses four project corridors affecting 62 traffic
8
5-22-23
signals in the City of Alhambra along Garfield Avenue, Fremont Avenue, Atlantic
Boulevard, and Valley Boulevard. These four corridors are funded under separate
LACMTA Measure R Funding Agreements but are being combined for the purposes of
this RFP because of identical preliminary design scope and objectives for all project areas
and to gain efficiency in preparation and review and in managing these projects. The
Alhambra Adaptive Traffic/Traffic Responsive Control Project (Garfield, Fremont, Atlantic
and Valley) is an eligible SR-710 North Corridor Mobility Improvement approved by the
Metro Board of Directors. The project will upgrade the traffic signal system, and other
components at major north-south and east-west corridors to improve the traffic operations
and mobility in the City. These improvements will be planned and developed in conjunction
with adjacent cities and Los Angeles County to ensure that traffic operations are
coordinated through major corridors within the SR-710 area. Staff is seeking to distribute
a Request for Proposals for professional engineering design services for the project.
Recommended Action: City Council authorize the distribution of a Request for
Proposals for Design Services the Traffic Signal Synchronization Project –
Adaptive/Traffic Responsive Upgrades Phase 1 with proposals due no later than 4:00 p.m.