City Council — Item 10
Original agenda text
Item
10. APPROVAL OF PROJECT NEUTRAL AGREEMENT WITH ERNEST BROWN &
COMPANY AND ZUSSER COMPANY, INC. FOR THE RESOLUTION OF DISPUTES
REGARDING THE JOHN ANSON FORD PARK INFILTRATION CISTERN PROJECT
The John Anson Ford Park Infiltration Cistern Project ("Project") was originally scheduled to be
completed by June 2022. The Project is behind schedule and is currently projected to be
completed by Fall 2023. This has led to various dispute claims being submitted on the Project,
which require the services of Ernest Brown & Company (Project Neutral) for a resolution.
Recommendation:
It is staff's recommendation that the City Council by motion adopt the attached Resolution approving
a Project Neutral Agreement ("Agreement").