Order of Business 1
1.k. Acceptance of Construction Work, Notice of Completion
and Approval of Contract Change Order No. 3 for Phase I
of the Placentia Public Safety Center Project, City Project
No. 5213 Fiscal Impact: Expense: $1,324,000.00 Original
Construction Contract $ 445,921.61 Contract Change
Orders $ 1,769,921.61 Total Construction Cost Budgeted:
$6,250,000.00 FY 2023-24 CIP Project Budget
Recommended Action: It is recommended that the City
Council:
1) Accept the work performed by TTS Construction, Inc.,
for Phase I of the Placentia Public Safety Center
Project, City Project No. 5213 for a grand total
amount of $1,769,921; and
2) Authorize the City Administrator to approve Contract
Change Order No. 3 in the amount of $328,755.43;
and
3) Authorize the City Administrator to file a Notice of
Completion with the Orange County Clerk-Recorder’s
Office for the Project; and
4) Authorize the City Administrator to release retention
funds in accordance with the terms of the contract.