Order of Business 7
a. PUBLIC WORKS CONTRACT WITH HARDY & HARPER, INC. (H&H) FOR
THE PALM DRIVE PAVEMENT REHABILITATION PROJECT FROM OBISPO
AVE. TO E. WILLOW ST. (PROJECT NO. 90.24003)
Summary:
The City Council will consider entering into a Public Works Contract with Hardy
& Harper, Incorporated (H&H) for construction of the Palm Drive Pavement
Rehabilitation Project from Obispo Avenue to East Willow Street (Project No.
90.24003). The Project includes the following elements:
· Approximately 49,700 square feet of asphalt pavement repair employing
a combination of reconstruction and grind/overlay;
· Removal and replacement of approximately 600 square feet of damaged
sidewalk and driveways;
· Removal and replacement of approximately 450 linear feet of curb and
gutter;
· Restoration of traffic striping and markings; and
· Upgrade of three curb ramps to comply with the American Disabilities Act.
Funds are available as designated in the FY 2023-24 Capital Improvement
Program (CIP) Budget for Pavement Management, utilizing funding from
Measure R (County), Measure M, Proposition C, and Road Maintenance and
Rehabilitation Act (RMRA). Expenditures for this Project will be allocated initially
towards Measure R, Measure M, and Proposition C to prioritize funds consistent
with expenditure deadlines.
Subject to City Council approval of the contract award, staff would issue a
Notice to Proceed and begin coordinating with the contractor. Staff anticipates
the project would begin construction in August 2023 and anticipates project
completion in November 2023.
Recommendations:
1. Authorize the City Manager to enter into a Public Works Contract with H&H
for construction of the Palm Drive Pavement Rehabilitation Project from
Obispo Avenue to East Willow Street (Project No. 90.24003), for a term of 50
working days and a not-to-exceed contract amount of $774,000 in a form
approved by the City Attorney.
2. Authorize the Public Works Director to utilize a contingency of up to 10%
($77,400) to accommodate additional scope of work in the event of changed
or unforeseen conditions, for a total construction budget of $851,400.