Santa Ana
City Council
16. Approve a Budget Reallocation and Award a Construction Contract to Onyx Paving
Company, Inc. in the Amount of $5,204,000 for the Fremont Elementary and Spurgeon
Intermediate Safe Routes to School Project, with an Estimated Project Delivery Cost
of $6,505,000 (Project No. 206964) (NonGeneral Fund)
Department(s): Public Works Agency
Recommended Action: 1. Authorize budget reallocation of $1,656,000 in unspent
Roadway Maintenance and Rehabilitation Account (SB1) from the Fairview Avenue
Rehab, the South City Limit to Segerstrom Avenue, FY 202021 (No. 216978)
Project to construction funds for the Fremont Elementary and Spurgeon Intermediate
Safe Routes to School (Project No. 206964).
2. Award a construction contract to Onyx Paving Company, Inc., the lowest
responsible bidder, in accordance with the base bid in the amount of $5,204,000,
subject to change orders (nottoexceed up to 25% of the base bid amount) in
accordance with the Greenbook: Standard Specifications for Public Works
Construction, for construction of the Fremont Elementary and Spurgeon Intermediate
Safe Routes to School Project, for a term beginning July 18, 2023, and ending upon
project completion, and authorize the City Manager to execute the contract subject to
nonsubstantive changes approved by the City Manager and the City Attorney.
3. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$6,505,000, which includes $5,204,000 for the construction contract, $780,600 for
contract administration, inspection and testing, and a $520,400 project contingency
for unanticipated or unforeseen work.
4. Approve an amendment to the FY 202324 Capital Improvement Program to
include $1,656,000 in unspent Road Maintenance and Rehabilitation Account (SB1)
funds.
5. Determine that the recommended actions are exempt from further review in
accordance with the California Environmental Quality Act as Categorical Exemption
Environmental Review No. ER202032 was filed for the project.