Agenda Item
· Alhambra
City Council — Item 9
Original agenda text
Item
9. AWARD CONTRACT: WELL NO. 12 PUMP REPLACEMENT – F2M23-57, C2M23-56,
M2M23-115
Well No. 12 is a critical producer of potable water for the City. The well produces
approximately 500 gallons per minute; production that is vital to maintaining an adequate
water supply for the City. In December of 2022, Well No.12 experienced a shaft issue that
required the pump to be pulled out of the ground. Staff solicited bids from qualified
vendors, with only two responding. Tri County Pump was the low bid to pull and inspect
the pump. The pump that was pulled is 14 years old; upon inspection it was determined
the pump, shaft, and column piping need to be replaced.
6
7-24-23
Recommended Action: City Council award a contract, subject to final language
approval by the City Manager and City Attorney, to Tri County Pump for the Well No. 12
Pump Replacement in an amount not to exceed $103,663.80; direct the Finance Director
to carry over the remaining $142,282.00 balance of account 401.80.8884.90837 from
Fiscal Year 2022-2023 to the 2023-2024 Fiscal Year Budget; and, direct staff to undertake
the steps necessary to finalize Council’s action. (M2M23-115)