Order of Business 14
a. CONTRACT AMENDMENT REGISTER DATED JULY 25, 2023
Summary:
The Contract Amendment Register is a listing of proposed contract amendments
and project change orders eligible for streamlined processing based upon the
following criteria as documented in the City’s Purchasing Policy:
· Funds have been authorized as part of the adopted fiscal year Operating
Budget.
· Staff are satisfied with the goods/services received to date; and
· City Manager reviewed and approved each amendment for streamlined
processing.
The contract amendments being presented for City Council consideration are as
follows:
FCG Consultants, Incorporated: Services for Spring Street Bicycle Lane Gap
Closure project (90.18003). Amendment No. 2 extends the term by nine months
through September 30, 2023, and increases the compensation by $41,019.56
due to project delays and additional services. The revised total not-to-exceed
contract amount is $322,712.56.
Tetra Tech, Incorporated: Services for Well 10 Construction project (95.18011).
Amendment No. 2 extends the term by 5 months through November 30, 2023,
and increases the total compensation by $17,000 to a new not-to-exceed
contract amount of $475,000 for additional services for permit information.
Architerra Incorporated dba Architerra Design Group: Professional design
services for Hillbrook Park Renovation Design project (80.23007). Amendment
No. 1 extends the term by 8 months through March 30, 2024, due to scheduling
delays and to provide additional support services.
SWA Group, Incorporated: Professional architectural design services for the
Citywide Median Landscape project (90.23006). Amendment No. 1 extends the
term by 10 months through May 30, 2024, due to scheduling delays and provide
additional support services; the amendment does not provide additional
compensation.
Recommendation:
Authorize the Contract Amendment Register dated July 25, 2023.