Walnut

City Council

11. FY 2022-23 Concrete Repair Project – Award of Contract Recommendation: That the City Council: 1. Award a construction contract for the FY 2022-23 Concrete Repair Project to FS Contractors, Inc. in the amount of $238,650; 2. Reject all other bids; 3. Appropriate $138,270 from restricted Proposition C Fund Reserves (13) to the City-wide Sidewalk Project ($128,270 to 13-6127-6227 and $10,000 to 13- 6217-6216); 4. Appropriate $54,250 from restricted Park In-Lieu Fund Reserves (06) to the City-wide Sidewalk Project (06-6127-6227); 5. Authorize staff to issue a Purchase Order to FS Contractors, Inc. in the amount of $238,650; 6. Authorize staff to issue change orders not to exceed 10% of the contract award amount ($23,865) to FS Contractors, Inc.; and 7. Approve a Purchase Order to RKA Consulting Group in the amount of $30,000.