Item
56. Del Valle Grading Project Construction Contract
Recommendation: Find that the Del Valle Grading Project, Capital Project (CP)
No. 89159 (Project), located at 28101 Chiquito Canyon Road in Castaic (5), is
within the scope of the previously adopted Negative Declaration for the Project
under the California Environmental Quality Act; approve the Project (Project),
with a Project budget of $1,326,000; approve an appropriation adjustment to
transfer $826,000 from Del Valle New Infrastructure, CP No. 89034, and
$500,000 from Del Valle Various Mitigation/Remediation Projects, CP No.
89040, to the Project, to fully fund the Project; adopt the plans and
specifications, and advertise for bids to be received by 10:00 a.m. on
September 11, 2023; and authorize the Director of Public Works to take the
following actions: (Department of Public Works) ADOPT
Execute a consultant services agreement with the apparent lowest
responsive and responsible bidder to prepare a baseline schedule for an
amount not to exceed $5,000, funded by the Project funds;
Determine that a bid is nonresponsive and reject a bid on that basis,
award the next lowest responsive and responsible bidder, waive
inconsequential and nonmaterial deficiencies in bids submitted, and
determine, in accordance with the applicable contract and bid
documents, whether the apparent lowest responsive and responsible
bidder has timely prepared a satisfactory baseline construction schedule
and satisfied all conditions for contract award, and upon that
determination, award and execute a construction contract to the apparent
lowest responsive and responsible bidder, if the low bid can be awarded
within the approved total budget, establish the effective date of the
contract upon receipt of acceptable performance and payment bonds
and evidence of required contractor insurance, and take all other actions
necessary and appropriate to deliver the Project;
Execute any easements, permits, and utility connection agreements
necessary for the completion of the Project, provided that the costs
related to these easements, permits, and agreements do not cause the
Project to exceed the approved Project budget; and
Carry out, manage, and deliver the Project on behalf of the Consolidated
Fire Protection District, award and execute consultant agreements,
amendments, and supplements within the same authority and limits
delegated to the Director of Public Works by the Board for County
Capital Improvement Projects, accept the Project, and release retention
upon acceptance. (23-2759)