7. RESOLUTION NO. ____________ - APPROVAL OF AN AGREEMENT WITH YUSEN
TERMINALS LLC. TO IMPLEMENT A ZERO EMISSION YARD TRACTOR
DEMONSTRATION PROJECT
Summary: Staff requests approval of an agreement with Yusen Terminals, LLC. to implement a
zero-emission yard tractor demonstration project. The Project requires YTI to demonstrate two
zero-emission yard tractors at the terminal property for three years in order to satisfy an
environmental requirement contained in Permit No. 692 identified as “Lease Measure AQ-4:
Zero or Near-Zero Emissions Demonstration Project.” The Agreement sets out the respective
costs and responsibilities between the City of Los Angeles Harbor Department and YTI. YTI is
required to lease the demonstration equipment from its selected vendor and conduct the
demonstration with periodic reports to the Harbor Department. The Harbor Department is
required to install electrical charging infrastructure, reimburse YTI for the equipment lease
payments and other related costs, and provide administrative oversight for the Project. The
Harbor Department will be financially responsible for all costs of the Project specified in the
Agreement, including equipment lease costs, infrastructure equipment installation, and
maintenance costs for a total estimated cost of $1,500,000.
Recommendation: Board resolve to (1) find that the Director of Environmental Management has
determined that the proposed action is administratively exempt from the requirements of the
California Environmental Quality Act (CEQA) under Article II Section 2(i), of the Los Angeles City
CEQA Guidelines; (2) approve the Agreement between the City of Los Angeles Harbor
Department and Yusen Terminals, LLC.; (3) direct the Board Secretary to transmit the
Agreement to the City Council for approval pursuant to Charter Section 373; (4) authorize the
Executive Director to execute and the Board Secretary to attest to said Agreement upon approval
by City Council; and (5) adopt Resolution No. __________________ .