Item
10. NOTICE INVITING BIDS: REHABLITATION OF THE SEWER MAIN ON BEACON
STREET – F2M23-61, N2M23-104
The City of Alhambra Utilities Department is responsible for inspection, maintenance and
repair of the sewer system. The Wastewater Division performs regular sewer main
cleaning and has an ongoing program to monitor and inspect the condition of the City’s
sewer collection system. Extreme rain events over the past few months have further
degraded the condition of an aging sewer pipeline. On June 6, 2023, at 1010 E. Beacon
Street, the sewer main became blocked causing sewage to overflow through a manhole
into the street. City’s staff contained the spill and worked to clear the blocked sewer main.
Lining this section of the sewer main will reduce the risk of future potential blockages and
avoid the risk of pipe failure. Due to the sewer main passing through many private
properties, pipe lining is the preferred method of repair. This section of sewer main is 6
inches in diameter and about 570 feet in length. Plans and specifications have been
6
8-28-23
prepared; staff has reviewed the plans and found them to be consistent with City
standards.
Recommended Action: City Council approve the distribution of a Notice Inviting Bids
to qualified contractors for the Rehabilitation of the Sewer Main on Beacon Street with
bids due no later than 10:30 a.m. on September 14, 2023, and opened at 11:00 a.m. that
same day.