Agenda Item
· San Diego
City Council — Item 51
Original agenda text
Item
Item 51: Authorize an Extension of Contractual Obligations with Dick Miller Inc for
Construction of Maple Canyon Restoration - Phases 1 & 2.
Total Estimated Cost of Proposed Action and Funding Source:
If the City Council approves the 60-month LTMMA, the total amount of the Contract will
be increased by $315,000.00 to a total of $10,080,552.60.
The total bid amount of $10,080,552.60, including the $315,000.00 for work under 60-
month LTMMA, has been certified by the Department of Finance, and this amount has
been encumbered in the Contract Purchase Order.
Council District(s) Affected: 3.
Proposed Actions:
(O-2024-15)
Introduction of an Ordinance authorizing the Mayor, or his designee, to extend the
contractual obligations in Contract K-23-2030-DBB-3 with Dick Miller, Inc. for an
amount not-to-exceed $315,000 to provide habitat restoration services through a 60-
Month Long-Term Maintenance and Monitoring Agreement related to the Maple Canyon
Restoration - Phases 1 and 2 project.
6 votes required pursuant to Charter Section 99.
Committee Actions Taken:
This item was heard at the Active Transportation and Infrastructure Committee meeting
on July 13, 2023.
ACTION: Motion by Vice Chair LaCava, second by Committee member Montgomery
Steppe, to recommend Council approval of staff’s proposed actions.
VOTE: 4-0; Lee-yea, LaCava-yea, Montgomery Steppe-yea, von Wilpert-yea.
Engineering & Capital Projects: Elif Cetin, (619) 533-3794
City Attorney Contact: Frank Ahn