Agenda Item · Placentia

City Council — Item E

Placentia October 03, 2023 City Council Item E
Original agenda text Order of Business 1
1.e. Staff Report - Change Orders for TOD Crowther Sewer Line 1.e.1 Change Order No. 8 1.e.2 Change Order No. 9 Expense: $ 4,696,973.63 Original Construction Contract $ 469,697.36 Contingency Amount $ 136,481.16 Contract Change Order No. 8 And 9 $ 5,303,152.15 Total Contract Amount with Change Orders Budget: $ 5,445,645.90 Total Project Budget $ 3,829,676.56 9/29/23, 1:31 PM placentia.granicus.com/GeneratedAgendaViewer.php?view_id=4&event_id=429 (103101-6750) ARPA Funds $ 1,615,969.00 (713101- 6750) TOD Sewer Development Impact Fees Recommended Action: It is recommended that the City Council: 1) Authorize the City Administrator to approve Contract Change Orders Nos. 8 and 9 with Kana Construction Inc. in the amount of $136,481.16; and. 2) Authorize the City Administrator and/or his designee to execute all necessary documents, in a form approved by the City Attorney.