8. CONSIDERATION AND APPROVAL TO AWARD A CONSTRUCTION
CONTRACT FOR CIP 2019-02 SLAUSON AVENUE CONGESTION RELIEF
PROJECT
RECOMMENDED THAT CITY COUNCIL:
1. Award the contract to All American Asphalt for the construction of CIP 2019-02
Slauson Avenue Congestion Relief Project as the lowest responsive, responsible
bidder for a not to exceed fee of $5,650,337.79 (Option 1) payable from
reimbursable Metro Measure R grant funds; and
2. Approve a construction contingency in the amount of $680,277.21 payable from
reimbursable Metro Measure R grant funds; and
3. Authorize the Finance Department to allocate funds into a project account number
that will pay for the project while staff seeks reimbursement from Metro; or
4. Award the contract to All American Asphalt for the construction of CIP 2019-02
Slauson Avenue Congestion Relief Project as the lowest responsive, responsible
bidder for a not to exceed fee of $9,143,090.77 (Option 2), which includes
concreting five intersections where traffic signals will be upgraded and partially
paid from reimbursable Metro Measure R grant funds; and
5. Approve a five percent (5%) construction contingency in the amount of
$457,154.54 payable from designated funds chosen by the City Manager’s Office
and Finance Department if Option 2 is chosen; and
6. If the City Council elects to go with Option 2, authorize the City Manager’s Office
and Finance Department to issue an account number and utilize designed funds
to pay for the remaining balance ($3,269,630.31) and complete the Option 2
Project; and
7. Authorize the City Manager to execute the construction contract agreement and
all applicable change orders in good faith.