c. PUBLIC WORKS CONTRACT WITH TTS ENGINEERING INCORPORATED
FOR THE 33RD STREET WATER MAIN REPLACEMENT PROJECT
(PROJECT NO. 95.22003)
Summary:
The City Council will consider authorizing the City Manager to enter into a Public
Works Contract with TTS Engineering Incorporated (TTS) for the construction of
the 33rd Street Water Main Replacement Project, in the amount of $2,317,861
with a contingency up to $129,335.40. In March 2023, the City released this
project out to bid with the original scope of work, which resulted in the rejection
of bids due to bid irregularities. Consequently, the City revised the scope of work
and re-released a Notice Inviting Bids (NIB) on October 13, 2023, with a bid due
date of November 3, 2023; the City received nine bids by the deadline. Following
review of bids, staff determined TTS is the lowest responsive and responsible
bidder with the proper experience to perform the water main pipeline
replacement on 33rd Street and related work identified in the NIB and contract
documents. Subject to City Council approval of the contract award, staff would
issue a Notice to Proceed and begin coordinating with the contractor.
Construction of the project is estimated to start in January 2024 with completion
within 120 working days.
Strategic Plan Goal(s):
Goal No. 4 Infrastructure: Maintain and improve the City’s physical
infrastructure, water system, and recreational spaces.
Recommendations:
1. Authorize the City Manager to enter into a Public Works Contract with
TTS for the construction of the 33rd Street Water Main Replacement
Project (Project No. 95.22003), for a term of 120 working days, for a
not-to-exceed contract amount of $2,317,861, in a form approved by the
City Attorney; and
2. Authorize the Public Works Director to utilize a contingency of up to
$129,335.40 to accommodate additional scope of work in the event of
changed or unforeseen conditions and utilize remaining American
Rescue Plan Act funds, for a total construction budget of $2,447,196.40.