10. NOTICE OF COMPLETION: ALHAMBRA PARK RESTROOM PROJECT – F2M22-66,
C2M23-9, M2M23-192
On February 13, 2023, the City Council awarded a contract to Sanz Construction Inc. for
the Alhambra Park Restroom Project in the amount of $342,930.00. There were two
change orders, the first in the amount of $37,330.00 was for multiple unforeseen issues
which included: additional framing due to extensive termite damage, the installation of a
water line for floor drains, removal and disposal of extra concrete to gain ADA compliance,
re-installation of electrical subpanel to meet Building Code requirements and the removal
of existing security gates and installation of custom sliding security gates to gain ADA
compliance. The second change order in the amount of $8,617.61 was to replace an
adjacent broken water fountain/water fill station. After change orders, the total amount of
the contract cost was $388,877.61. This project has been inspected by staff, and all work
has been completed in accordance with the City’s requirements and specifications. As
such, it is appropriate for the City Council to accept this project as complete.
Recommended Action: City Council accept the work of Sanz Construction Inc. for
the Alhambra Park Restroom Project as complete in the amount of $388,877.61; direct
the City Clerk to file a Notice of Completion with the County of Los Angeles for recordation;
instruct the Finance Director to release the 5 percent retention 35 days from the date of
recordation if no liens are filed; and, direct staff to undertake the steps necessary to finalize
Council’s action. (M2M23-192)